Development & Timescale Objectives

STAGE 1: Draining and levelling the field together with car parking. Having raised over £100,000, BRCA has drained and levelled the field in 2014 with local residents being kept advised of specific details. The objective is for it to be in use by Brassington Football Club and for other field activities by April 2015.

 

STAGE 2: Multi-Use Games Area for tennis, volleyball, five-a-side etc. A grant has been obtained to build this and it is planned to have it in use for the summer of 2015.

 

STAGE 3: A pavilion with changing rooms, showers and indoor recreational activities. Funds for this may become available depending on the outcome of planning permission for wind turbines at Longcliffe. Otherwise other sources of funds will be required.